The progress of the construction of the South Ring Road (JLS) in Sampang is said to be still at 48 percent, more than four months ahead of the end of the contract period. Data collected by jatimnow.com shows that the JLS project was carried out by PT. Asri Karya Lestari with a budget of IDR 204.5 billion. The road being worked on is 6.3 kilometers long. Public Relations PT. Asri Karya Lestari, Hairul Mofid said that the work progress had reached 46 to 48 percent. However, in about a week, he is optimistic that it will reach more than 50 percent. “For now it is still around 48 percent. But from the work that is still in process, soon it will be more than 50 percent,” Hairul explained that JLS work had indeed started from scratch. Especially in the cultivation of land that is still in the form of agricultural land.